Porter Park today
The site plan for Porter Park is now approved and the project team is preparing for construction in early 2027 as weather allows.
Located at 731 Tabor St., Porter Park is a 7.7-acre property purchased in 2021 by the city to provide much needed park space in Ward 1.
To honor the legacy of the Porter family, the park is named after Daniel Wilson Porter and Phyllis Porter. Daniel and Phyllis owned this property and had a love for farming and preservation; Daniel became a master gardener late in life. The Porter family desired the city carry on the farming tradition on the property, with a farming element in the future park that would serve the Lakewood community. The city agreed to incorporate an agriculture theme, and as always, is committed to sustainability. Nearby residents can anticipate lots of open space, native plantings and modest amenities in their new neighborhood park.
Demolition of the existing structures on the site occurred in early 2023. The development of the site was initially funded in the city's five-year Capital Improvement Plan Budget in 2025-2026, but has been delayed to start construction in 2027 due to resource constraints.
Residents have provided feedback and helped create a vision for the new park through a two- year community engagement process to develop a final site plan. The site plan is now approved and includes a loop trail, open lawn area, nature playground, community garden and a pollinator garden. In addition, the project was awarded a Community Development Block Grant to support the development of the site!
The site plan for Porter Park is now approved and the project team is preparing for construction in early 2027 as weather allows.
Located at 731 Tabor St., Porter Park is a 7.7-acre property purchased in 2021 by the city to provide much needed park space in Ward 1.
To honor the legacy of the Porter family, the park is named after Daniel Wilson Porter and Phyllis Porter. Daniel and Phyllis owned this property and had a love for farming and preservation; Daniel became a master gardener late in life. The Porter family desired the city carry on the farming tradition on the property, with a farming element in the future park that would serve the Lakewood community. The city agreed to incorporate an agriculture theme, and as always, is committed to sustainability. Nearby residents can anticipate lots of open space, native plantings and modest amenities in their new neighborhood park.
Demolition of the existing structures on the site occurred in early 2023. The development of the site was initially funded in the city's five-year Capital Improvement Plan Budget in 2025-2026, but has been delayed to start construction in 2027 due to resource constraints.
Residents have provided feedback and helped create a vision for the new park through a two- year community engagement process to develop a final site plan. The site plan is now approved and includes a loop trail, open lawn area, nature playground, community garden and a pollinator garden. In addition, the project was awarded a Community Development Block Grant to support the development of the site!
Share When will you start this project? on FacebookShare When will you start this project? on X (formerly Twitter)Share When will you start this project? on LinkedinEmail When will you start this project? link
When will you start this project?
SandraP
asked
almost 2 years ago
Hi there,
Thank you for your question regarding Porter Park. The project team is also anxious to get this park under construction. Fortunately, this project has been awarded funding from the Community Development Block Grant program. With this funding comes some additional review requirements that have caused some delay. In addition, the park design is currently in engineering and permitting review. This project is funded in the current budget cycle and is anticipated for construction in spring of 2026. Thank you for your patience!
Share Hi! Is there any update on this park? Is it forever off of the table, or might construction happen down the road? We were looking forward to seeing the plans come to life and being able to play there, plus the increase in property values, but maybe it is scrapped forever? Thanks for any update! on FacebookShare Hi! Is there any update on this park? Is it forever off of the table, or might construction happen down the road? We were looking forward to seeing the plans come to life and being able to play there, plus the increase in property values, but maybe it is scrapped forever? Thanks for any update! on X (formerly Twitter)Share Hi! Is there any update on this park? Is it forever off of the table, or might construction happen down the road? We were looking forward to seeing the plans come to life and being able to play there, plus the increase in property values, but maybe it is scrapped forever? Thanks for any update! on LinkedinEmail Hi! Is there any update on this park? Is it forever off of the table, or might construction happen down the road? We were looking forward to seeing the plans come to life and being able to play there, plus the increase in property values, but maybe it is scrapped forever? Thanks for any update! link
Hi! Is there any update on this park? Is it forever off of the table, or might construction happen down the road? We were looking forward to seeing the plans come to life and being able to play there, plus the increase in property values, but maybe it is scrapped forever? Thanks for any update!
Tgrchrm
asked
12 months ago
Hi there,
Thank you for your question regarding Porter Park. The project team is also anxious to get this park under construction. Fortunately, this project has been awarded funding from the Community Development Block Grant program. With this funding comes additional review requirements that have caused some delay. In addition, the park design is currently in engineering and permitting review. This project is funded in the current budget cycle and is anticipated for construction in spring of 2026. Thank you for your patience!
Fall 2022 - Demolition and hazardous tree mitigation begins.
Porter Park Development has finished this stage
The existing structures and any hazardous trees are removed.
Spring 2023 - Project launch
Porter Park Development has finished this stage
Public engagement and an initial residents’ needs survey on the development of the property into a park begins.
Summer 2023 - Porter Park Open House May 17
Porter Park Development has finished this stage
Join us on Wednesday, May 17 from 5:30 to 7 p.m. for the Porter Park Open House. Residents will have an opportunity to tour the site, review survey results and provide input on initial concepts.
Spring 2024 - Design Concepts Open House May 1
Porter Park Development has finished this stage
Residents are invited to share their thoughts on design concepts and playground amenities for Porter Park on Wednesday, May 1, from 5:30 to 7 p.m. Enjoy ice cream in the park!
Spring 2027- Construction begins
Porter Park Development is currently at this stage
Construction of future park amenities for Porter Park has been delayed to begin in the spring of 2027 due to resource constraints in 2026. Rest assured, the park site plan is approved thanks to community feedback and construction will begin in 2027 as soon as weather allows. Thank you for your patience!